The steel beams have been erected once again and measurements have been taken and sent to the contractor who will install the enclosure. It will take 6-8 weeks for some of the panels to be delivered as it is coming from Europe.
The good news is work on the enclosure will still proceed in April. The drain pipes from the existing roof have now been redirected to the mechanical room. The roof on the mechanical room is now complete and final brickwork will commence the first week of April. In the middle of April, the doors for the boys and girls changeroom will be installed.
The pool will soon be drained of any water and prepped for the pool contractor to continue finishing the inside of the pool. Once complete, the concrete will be poured around the pool. This is needed so the pool can be covered with boards to allow roof work on enclosure to be done.