March is officially here and a lot of transformations will be happening in the pool area. The rubber surfacing was delayed last week as the drains on the pool's deck needed further adjustments. They have already started this Monday and will finish by the weekend. Once the rubber is cured, the pool contractor will begin preparing the surface of the pool and within a week, be able to fill the water and start the pump.
There are only a few items that need fixing and we hope to take care of them in the next few weeks.
Final inspections will also take place once all the work is completed. If everything goes well, we would like to start the swim program end of March. Mrs. Scarlett has started preparing the bulletin board in front of the changerooms for parents who wish to learn about Northstar’s unique swim program.